Solar ordinance issued: three-party contracts required, strict penalties for theft and vandalism
It covers solar systems of up to 5 MW: rooftops, courtyards, tea gardens, unused land and floating solar. A standard contract between the consumer, the provider and the authority is required.
- Up to 5 MWSystems covered
- 3 partiesStandard contract
- Up to 5 yearsPrison for vandalism
What was issued
In October 2026 the gazette of the Special Solar Power Installation Ordinance 2026 was published. Its aim is to get small and medium solar systems installed quickly and safely.
Which systems it covers
- Solar systems of up to 5 MW: rooftops, courtyards, unused land, tea gardens, floating solar and solar over farmland (agrivoltaics).
- Large ground-mounted solar parks are excluded.
Your rights in writing
A standard three-party contract between the consumer, the service provider and the authority is required, so who is responsible for what is written down.
Penalties
- Theft of solar equipment: up to 3 years in prison and a fine of up to Tk 50,000.
- Vandalism: up to 5 years in prison and a fine of up to Tk 5 lakh.
- Illegal connection: up to 3 years in prison and a fine of up to Tk 5 lakh.
Oversight
A National Policy Council headed by the Prime Minister will oversee it, with committees at district and upazila level.
On 2 November the Cabinet approved a draft Act to make these rules permanent law. We will update this item when the Act is passed.
How much could this help on your roof?
GRACE is a government-enlisted solar provider. After seeing your roof we can tell you the right size, the cost and the paperwork route.
Sources
- Dhaka Tribune
- Official notice / gazetteLink added once it is published
Disclaimer: This is GRACE’s own summary of the original sources, not legal or financial advice. Final terms are set by the authorities and lenders.